National Park Service · Death Valley

Skyline Unit 122 Rehabilitation

Public view · read only
ProjectDEVA Skyline Unit 122
RolePM / Superintendent
ScheduleMon–Fri · 10-hour shift
SourceMPP revision 8 · Aug 1, 2026

Command Center

Today’s project picture—without the scavenger hunt.

Schedule activities, federal documentation, procurement, quality control and field follow-through in one place.

Contract deadlineTBDSet after NTP and accepted baseline
0

In progress

!
0

Awaiting review

×
0

Blocked / action

0

Complete

Priority control log

0 tracked items from the Skyline schedule and project controls

TypeIDItem / ActivityResponsible partyDuePriorityStatus
Loading the job board…

NPS control point

Documentation that keeps the work moving

  • APP, Site Inspection Plan, WMP and environmental package
  • Archaeological monitor release before ground disturbance
  • Daily reports, certified payroll, inspections and photo records
  • RFI/submittal aging and procurement lead-time follow-up

Known schedule risk

SCE service + PV/BESS coordination

Third-party utility fees or owner-directed allowance remain TBD pending utility engineering review. Keep this visible until contract responsibility and amount are resolved.